Eastern Creek Compost Refining Line, NSW

Year:
2026 - ECI Phase 2, Detailed Design Underway
Location:
Sydney, NSW
Client:
Cleanaway Waste Management

PROJECT OVERVIEW

Cleanaway’s Eastern Creek facility already processes food and garden organics (FOGO) into compost. The proposed refining line is the next stage. It would take composted material from the existing compost hall and produce a clean, high-value product that meets the NSW EPA Compost Order 2016 and AS 4454. Since late 2024, the project has moved through a series of defined stages. Each one ends at a design and commercial decision point, giving Cleanaway what it needs to decide whether, and how, to proceed.

OREZ SCOPE

Cleanaway brought OREZ in under an Early Contractor Involvement (ECI) agreement in late 2024, while the refining line was still a concept. That early start shaped everything after it. OREZ didn’t price a fixed design. Instead, it worked with Cleanaway to define the project from the ground up, starting with a set of design requirements owned jointly by both teams.

Since then, each stage has built the case for the next. Feedstock modelling and a techno-economic assessment narrowed the field to a preferred configuration. A Process Design Strategy then locked in the agreed basis. Concept design and HAZID brought safety and operability in while change was still affordable. Each stage closes with a defined gate, a clear design and commercial basis for Cleanaway to decide whether to proceed, pause or change course. Cleanaway gave the green light at the end of Phase 1, and Phase 2 of the ECI, detailed design, is now underway.

TECHNOLOGY

At its core, the refining line is a decontamination process. FOGO compost carries plastics, glass, metals and other physical contaminants from the collection stream. The line is engineered to remove them so that saleable product meets the physical contaminant limits of the NSW EPA Compost Order and AS 4454. The process combines buffered feed, staged screening, multi-stage contaminant removal and size reduction, with quality assurance built in before product leaves the site. Size reduction recovers clean oversize material, so more saleable compost comes from the same feedstock without compromising quality.

Three principles shape the design:

  • Compliance comes first: product quality takes priority over raw yield.
  • It is built for real-world conditions, including wet weather and changing feed.
  • It is practical to run and maintain safely.

Refining lines rarely get a clean slate. Retrofitting into an operating facility means designing around existing infrastructure, live operations and a fixed footprint, constraints a greenfield site never imposes. OREZ has worked through these brownfield challenges on previous projects, and that experience shapes a design that works with Cleanaway’s site rather than reshaping it.

NEXT PHASE

With the Basis of Design Freeze complete, OREZ is taking the design through 70%, 90% and Issued for Construction stages. Safety in Design, HAZOP, constructability, and maintainability workshops are running alongside, supported by a virtual reality model for operator and maintainer walkthroughs. Once detailed design is complete, the proposed next step is delivery of the Works, subject to Cleanaway’s approvals and investment decision. As at every stage so far, that decision sits with Cleanaway.